Explain Cutover Activities/Strategies in SAP FI.

Cutover Activities or Master Data Uploading Strategies Depending upon the when we are going live. As per that, you have to give the information to your core team. If you goling live at the middle you have to upload the all P&L Account items and B/S Items. If you going live at the financial year start, you have to only Upload the B/S Items. Activities for Golive:

1. G/L Master Upload Thru BDC or LSMW (TC-Fs00 and extended one co code to another company code Fs01)
2. Vendor Master Upload Thru BDC Or LSMW (Will be Taken Care By MM)
3. Customer Master Upload Thru BDC or LSMW (Will be Taken Care By SD)
4. Asset Master Upload(Thru As90)
5. Cost Element Master Upload
6. Cost Center Master Upload
7. Profit Center Master Upload
8. G/L Balances Thru F-02
10. Vendor Balances thru F-43
11. Customer Balances thru F-22
12. Customer Advances thru f-29
13. Vendor Advances thryu F-48

Before uploading Vendor Balances you have to take care of WHT(TDS) Information. *-- Satynarayana

Difference between the User Exit & Gap analysis.

Both are quiet a different and has a small relation.

User exits are standard gate ways provided by SAP to exit the standard code and we can write our own code with the help of ABAP workbench. its not new functionality which we are trying to build in sap but its slight enhancement within the same code.

Gap analysis is start point of Realization and once blue print is finished we have to find the realization of sap system for client requirment and there will be certain gaps when compared to system fit. Those gaps can be closed either by re-engineering of business process to fit with SAP or we have to use USER exits in case of small deviations or complete enhancements with the help of ABAP to fit with the SAP system. *-- V. Sridhar

What is roll out of SAP Project?

As per dictionary, Rollout means “Inauguration or initial exhibition of a new product”.

As per SAP specific definition, rollout is the strategy for international SAP implementation. Rollout strategy normally include the following
- Whether to implement SAP simultaneously (also known as big-bang) in all the countries, or
- Go live in sequence of phased manner
- Or to go for the combination of both (phased manner implementation for some of the countries and big-bang for others).

Rollout strategy is the most important decision that a client can make during SAP implementation. Normally, steering committee decides the rollout strategy.